"Forest Village A" project
Construction of a mixed-use real estate complex comprising 1,554 housing units, 1 office space, 2 shops, and 155 parking spaces, including 63 on the ground floor and 92 underground.

Project characteristics

  • Construction site address: Forest
  • Duration of the project: 2024 for a period of 640 working days
  • Cost of works: €23,617,046.85
  • Project owner: Bouygues Immobilier Belgium
  • Architect: Symetry
  • Association: No

"Forest Village B&C" project
Construction of two buildings comprising 94 apartments, one nursery, three office units, four shops, one production facility, and 120 underground parking spaces.

Project characteristics

  • Construction site address: Ath
  • Duration of works: November 2020 to November 2023
  • Cost of works: €14,779,038.1
  • Client: Bouygues Immobilier Belgium
  • Architect: Symetry
  • Association: No