Construction of a 2,070 m² building comprising a sail loft, offices, a classroom, staff rooms, workshops, changing rooms, technical rooms, and surrounding areas.
Project characteristics
- Duration of works: December 13, 2021 to December 21, 2023
- Cost of works: €5,305,524.55
- Client: Ministry of the Wallonia-Brussels Federation
- Architect: A.M. AGWA - ARTGINEERINGµ
- Association: No