Namur Expo construction site: the first major phase is nearing completion

Namur Expo is undergoing an extensive transformation with the complete energy renovation of halls 1 and 2, carried out by our teams.

Progress:

In hall 1, the suspended ceiling and LED lighting are almost finished. The fire protection network is well advanced and will be completed very soon. Installation of the sectional doors has begun, and the new exhibitor electrical cabinets are being installed.

On the roof of hall 2, the steel structure is almost complete, and the ventilation units and heat pumps are fully installed. Insulation and waterproofing are progressing well, and the ventilation connections have just started.

Inside hall 2, fire detection is complete, and the fire protection network and ventilation ducts are well advanced, as is the LED lighting. On the north façade, most of the timber boxes have been installed.

  • Architect: FP Architectes

  • Project Owner: BEP

  • Engineering firm: G.E.I

  • Partner: Dherte - Wust