Heading to La Louvière, at Institut Saint Joseph, where the Dherte teams continue to move the works forward!

Completed

  • Waterproofing of the refectory roof

  • Installation of the refectory window frames

In progress

  • Load-bearing concrete block masonry of the top floor (+3)

  • Facing brick masonry

  • Foam insulation and screed on the ground floor

Upcoming

  • Installation of the +3 floor hollow-core slabs

  • Installation of the tower's window frames

  • Scaffolding assembly for insulation and zinc cladding of the tower

  • Waterproofing of the +3 roof

  • Tiling of the refectory

The project: to provide the school with a new, more functional refectory, a tower with a staircase compliant with current standards for flow evacuation, and a new lift. A carefully designed architecture with a green roof, brick masonry for the refectory, and zinc cladding for the staircase-lift tower.

A construction site taking shape little by little, thank you to all the teams involved! 

  • Architect: Triede

  • Project Owner: Institut St Joseph/ St Donat

LLISJ.jpg